The intermediate model estimates software development effort in terms of size of the program and other related cost drivers parameters (product parameter, hardware parameter, resource parameter, and project parameter) of the project. Also, calculate the Average resource size and Productivity of the software for Organic project type.Īns : Given estimated size of project is: 300 KLOC For OrganicĮffort (E) = a*(KLOC) b = 2.4*(300) 1.05 = 957.61 MM Calculate the Effort, Scheduled time for development.